In development budget, how do I work it if I am adding additional rows. Just copy the entire row? Formulas come with it also correct.? I seem to be doing something wrong because sometime incomplete in red is showing up. If this isn’t possible, could you add this feature to the model?
I haven’t added functionality yet to add additional budget rows but plan to do so soon. You can attempt to do so manually, but if you do you will need to both copy all formulas down from an adjacent row plus add a new row in the same place on the SCurve Calc tab. Both the Budget tab and SCurve calc tabs work in conjunction.